A top-running, double girder overhead bridge crane installed in an underground U.S. Gypsum Company Shoals Mine in Indiana

Powerful Underground Overhead Crane System Built and Installed in a Gypsum Mine

Case Study

A 20 ton capacity overhead crane and hoist from R&M Materials Handling Inc., sold by Harriman Material Handling (HMH), has been built and installed by CraneWerks 400 ft beneath the surface at the U.S. Gypsum Company Shoals Mine in Indiana.

Process

Harriman Material Handling, a distributor for both R&M Materials Handling and CraneWerks, came to the team with a unique opportunity. CraneWerks designed a bridge that was built in two pieces so it could fit down a narrow mine shaft before it was welded together at the bottom.

A top-running, double girder bridge crane was chosen because it offers the same hook height as a single girder crane, which would require a higher ceiling. The height available is important because the hoist and trolley ride on top of the bridge girders rather than being suspended beneath the bridge girder. This gives the best hook height of any overhead bridge crane option, giving users the maximum amount of lift (distance that the hook can be raised above the floor below) available.

The top-running double girder bridge crane, principally chosen based on the short lead time offered by R&M Materials Handling and its Indiana-based distributor, CraneWerks, is being used to assemble and maintain equipment for the mine underground. It spans 35 ft and travels on a 62 ft long runway.

Challenges

“Being underground is its own challenge. Everything from pouring concrete to lifting the beams is difficult because you don’t have access to a lot of the equipment you would normally think of using. It’s constant problem solving.” – U.S. Gypsum

Challenges were encountered both on the surface and below ground. For instance, the shaft used to get equipment into the mine was much smaller than most of the machinery used below. A 35 ft bridge beam was too long to go down the shaft in one piece. HMH and CraneWerks had to find a way to get the crane components and steel underground.

Results

“We needed a crane capable of moving large pieces around for assembly of equipment in the mine, and the results suggest we found a solution. We could have acquired a few telehandlers that had the necessary weight capacities, but the EOT (electric overhead traveling) crane was the preferred option.” – U.S. Gypsum

The crane has been installed at the south end of the mine. The plan is to relocate the site’s maintenance facility to this location in the future.

The crane provides a lifting solution on a daily basis, raising mobile equipment components, typically weighing approximately 10 tons, around the area. U.S. Gypsum explained that loads are normally large pieces of fabricated steel components of a larger machine.

“We have trained around 10 people on how to use the crane. About four or five of them use it on a daily basis.” – U.S. Gypsum


Ready to optimize your lifting operations with tailored solutions like our mining industry client? CraneWerks is here to engineer custom lifting solutions that meet your unique needs, even in challenging spaces.

Contact us today for a personalized consultation and quote. Let’s work together to transform your lifting capabilities, enhance efficiency, and boost your bottom line. Don’t let space constraints limit your potential – reach out to CraneWerks now!

For more information:

CASE STUDY ARCHIVE

Emergency Rehab for Metal Finishing Plant

Optimizing Production with a Gorbel Super Structure

Undecking Process Optimized by Commercial Truck Dealer